Journal of Korean Society for Quality Management 1990;18(2): 81-. |
공통납기를 고려한 병렬기계 일정계획 |
이정환1, 노인규2 |
1동의대 산업공학과 2한양대 산업공학과 |
A Parallel Processors Scheduling Problems with a Common Due Date |
Jeong-Hwan Lee1, In-Gyu No2 |
1 2 |
|
|
|
ABSTRACT |
This paper considers a scheduling of a set of jobs on single and multiple processors, when all jobs have a common due date and earliness and lateness are penalized at different cost rates. The objective is to determine the optimal value of a common due date and an optimal scheduling to minimize a total penalty function. It is also shown that a schedule having minimum weighted completion time variances must be V-shaped. For identical processors, a polynomial scheduling algorithm with the secondary objectives of minimizing makespan and machine occupancy is developed and a numerical example is presented. |
|
|
|